Vertex Park

Location:
Emersons Green
Client:
Chancerygate (Bristol) Ltd
Duration:
8 Weeks
Completed:
1st December 2025
Value:
£180,000

A comprehensive programme of dilapidation repairs and refurbishment works delivered on a fast‑track 8‑week schedule, returning the unit to a high‑quality, lettable standard.

Work Completed:

  • Strip‑out of existing flooring, ceiling tiles, and branded tenant fit‑out
  • Full internal redecoration throughout the office and warehouse areas
  • Epoxy resin floor coating applied to 2,500m² warehouse space
  • Installation of new carpets and vinyl flooring
  • Electrical and M&E alterations to suit landlord requirements
  • Final testing, commissioning, and handover

Services
Include:

Construction
Mechanical
Electrical
Maintenance
Support

View More Case Studies

...proactive during the design phase, their performance on site and site supervision has been exemplary, with a very high level of interaction and office support from their Project Managers.

joe bloggs, client business
★★★★★